Building New Bases

IMG_9789.jpeg

Students mixing concrete to fill a base form built from 2x12 lumber

In cases where a tablet-style stone has broken off too closely to the engraving to be reset into the ground or where a stone has broken off from a base that was then lost, it may be necessary to create a new base for the marker.

This situation is the only time that concrete should be used in cemetery restoration. Generally, concrete is not suitable for preservation work because it is too rigid and does not match the expansion and contraction rates of typical grave marker materials. Using concrete to fix cracks will usually make them worse in the long term. Older markers that once fell and were then surrounded by concrete on the ground to keep them in place are often further damaged.

However, concrete can form the structure of a new base, into which a tablet is inserted with lime mortar providing a barrier between the marker material and the concrete.

Calculating the size of the new base depends on the size of the marker. There are no strict guidelines for how large bases should be, but they should be able to support the weight of the marker and provide adequate support to keep the marker upright. Most bases are going to be at least as heavy as the marker or heavier.

The following are example calculations for a marker that could be modified to suit similar situations. All measurements are approximate.

Marker Size

Width: 20 inches
Height: 50 inches
Depth: 2 inches

Slot Size (in which the marker will sit)
A margin of 0.25 inches on all sides will allow for mortar between the marker and concrete

Width: marker width + 0.5 inch = 20.5 inches
Height: 6 inches
Depth: marker depth + 0.5 inch = 2.5 inches
Slot Volume [void]: 307.5 cubic inches

Base Size

Width: marker width + slot width + 6 inches = 26.5 inches
Height: slot height x 2 = 12 inches
Depth: marker depth + slot depth + 6 inches = 8.5 inches
Volume: total volume - slot volume = 2395.5 cubic inches (1.39 cubic feet)

An 80lb bag of concrete mix will form about 0.6 cubic feet of set concrete.

Base Volume / Bag Volume
1.39 cu.ft. / 0.6 cu.ft. = 2.3 bags